The Department of Health is planning to fix costs for clinical negligence claims up to £25,000, it has emerged.

Minutes from the 8 July meeting of the Civil Procedure Rules Committee state there has been a ‘change of policy’ at the department and ministers intend to consult on claims up to the revised figure.

Advertisement

It had been expected fixed recoverable costs could be applied to claims worth as much as £250,000 – a figure opposed by many within the legal profession.

Amanda Stevens, chair of the Civil Procedure Rule sub-committee (CPRC) tasked with drafting court rules for fixed recoverable costs in clinical negligence cases, said the new threshold would take in up to 60% of cases.

Stevens said the material worked up by the subcommittee on a draft protocol and illustrative rules would be amended accordingly, although the date of the consultation on fixed costs is still unknown.

That consultation was first proposed more than a year ago when stakeholders were first canvassed for their opinions on the level at which fees should be fixed.

The issue has come to the forefront in recent weeks, with sections of the media launching a campaign to bring down claimants’ costs against the NHS.

The Department of Health today insisted no final decision on the proposed threshold has been made, and the issue of a limit will be one of the questions in the consultation.

Ministers are understood to want to implement changes as soon as possible once the consultation is complete.

Responding to last year’s ‘pre-consultation’ on cutting costs in negligence claims, the Law Society stressed that it does not oppose the principle of fixed costs provided they are set at a reasonable rate and apply only to genuinely low-value and straightforward claims.

Cases above [£25k damages] are almost certainly going to have levels of complexity that make fixed fees inappropriate and unfair,’ the Society warned.